Section 3 Engineering Process; Workflow - ABB Relion 670 series Engineering Manual

Version 2.2 iec
Hide thumbs Also See for Relion 670 series:
Table of Contents

Advertisement

1MRK 511 398-UEN C
Section 3
3.1
670 series 2.2 IEC
Engineering manual
Engineering process

Workflow

Save the work
between the
different steps
Supported
protocols
Signal engineering
CMT
ACT
Write configuration
to IED
IED
WRITE
End
IEC08000122 V6 EN-US
Figure 4:
IED engineering workflow
The described sequence in
dependencies of the steps. It is possible to do a different sequence based on the
available information at the time the project is started. This means that several
iterations may be needed to finish the project.
Setting up the PCM600 project
Start
Create plant structure
Project
Optional, can be used to add
HWT
additional hardware modules
Configure Ethernet ports,
ECT
Routes and Merging units
ACT/
Configure IED functionality
SMT
Parametrization
PST
Create Single line diagram
for local HMI
GDE
IEC 61850
IEC 61850
Export
configuration
tool
IET600
Import
Easy GOOSE
ACT
SMT
engineering
IED
WRITE
End
Figure 4
is a proposal based on practical experience and
Section 3
Engineering process
SEMOD58465-5 v13
Export SCL files, IED-level
CID files, etc. from PCM600
Import SCL files to IET600
and do signal engineering.
FPN
Export SCL files from
IET600.
Import SCL files, IED-level
CID files, etc. to PCM600
Make GOOSE connections
Write configuration
to IED
IEC08000122-6-en.vsd
29