2.2 Quick Setup Procedures:
(perform prior to operating the machine on a daily basis)
Considering that the machine has been setup by Maintenance Personnel, the following quick start
procedures should be followed before daily operation of the equipment.
Power off tasks (perform these tasks prior to turning on the power):
Clean the blue rubber roller, print rollers, perforation sensor, idler rollers and product contact surfaces
with a clean cotton cloth and alcohol.
Inspect the machine to ensure all guards, covers and funnels are in position.
Inspect the machine for maintenance issues and report issues such as loose or broken components, frayed
wires, etc. to maintenance personnel.
Check that the air pressure is set to 60 psi.
Power on tasks (perform these tasks after cleaning and inspecting the machine)
Threading: A threading diagram has been provided to illustrate the proper bag path through the machine.
It is recommended that the appropriate diagram be copied and mounted to the side cover of the machine.
Setup Cycle Operation: Prior to loading parts, place the bagger in the Start / Manual / Setup mode and
press the footswitch or touch the <Manl Cycle> button. Test the bag seals, seal location or other
inspection requirements.
Manual Cycle Operation (if applicable): If manually loading parts, load parts into the bag ensuring all
parts are going into the bag. Toggle the machine from Setup mode to Manl mode. Press the <Manl
Cycle> button on the screen. Inspect the bag seals, seal location or appearance and continue the bagging
operation.
Automatic Cycle Operation (if applicable): If loading automatically with a conveyor, counter or scale
infeed system, ensure auxiliary equipment is turned on and press the <Manl Cycle> button to start the
system. If all equipment in the system is operating properly, toggle the machine from the Manl mode to
the Auto mode.
2.3 Threading Diagrams
Several threading diagrams are available based on the configuration of the bagger or the options ordered.
Select the configuration: standard vertical, horizontal, or horizontal incline. Then, select with printer or
without. Finally, select single or double dancer. Double dancer is for longer bags. This manual may not
contain the proper threading diagram for your specially or custom configured machine. Please contact
Technical Support to obtain a copy of the correct threading diagram.