Care And Maintenance; Servicing And Maintenance Intervals; Cleaning The Machine - Pfaff POWERLINE 3741 Instruction Manual

Doku-seam-system
Hide thumbs Also See for POWERLINE 3741:
Table of Contents

Advertisement

3

Care and maintenance

.09
3

Servicing and maintenance intervals

.09.01
Clean the hook compartment ...............................Daily, several times if in continuous use
Check the oil level ........................................................... Daily, before starting the machine
Check/adjust the air pressure ......................................... Daily, before starting the machine
Clean the fi lter of the air fi lter/lubricator ........................................................... As required
3

Cleaning the machine

.09.02
The cleaning cycle required for the machine depends on following factors:
● Single or several shift operation
● Amount of dust resulting from the workpiece
It is therefore only possible to stipulate the best possible cleaning instructions for each indi-
vidual case.
Fig. 9 - 01
These maintenance intervals are calculated for the average running time of a
single shift operation. If the machine is operated more than this, shorter inter-
vals are recommended.
For all cleaning work the machine must be disconnected from the mains
by switching off the on/off switch or by removing the mains plug!
Danger of injury if the machine suddenly starts up .
Care and maintenance
To avoid breakdowns, the following cleaning
work is recommended for single shift ope-
ration:
● Open the bed slide and remove the bob-
bin.
● Clean the hook and hook compartment
daily, several times if in continuous use.
● Set the bobbin in position and close the
bed slide.
69

Advertisement

Table of Contents
loading

This manual is also suitable for:

Powerline 3745

Table of Contents