Vertical mount
Step 1: Position the IQ Cable
A. Plan each cable segment to allow drop connectors on the IQ Cable to align with each PV
module. Allow extra length for slack, cable turns, and any obstructions.
B. Mark the approximate centers of each PV module on the PV racking.
C. Lay out the cabling along the installed racking for the AC branch circuit.
D. Cut each segment of cable to meet your planned needs.
WARNING: When transitioning between rows, secure the cable to the rail to prevent
cable damage or connector damage. Do not count on the connector to withstand
tension.

Step 2: Position the junction box

A. Verify that the AC voltage at the site is within range.
240 VAC split-phase
208 VAC single-phase
NOTE: All 208 VAC installations require that you use the IQ Gateway to commission the
microinverters to propagate correct grid profile settings for 208 VAC trip points.
B. Install a junction box at a suitable location on the racking.
C. Provide an AC connection from the junction box back to the electricity network using
equipment and practices as required by local jurisdictions.
16
Enphase IQ8, IQ8+, IQ8M, IQ8A, and IQ8H Microinverters
Service type and voltage: L1-L2
© 2024 Enphase Energy Inc. All rights reserved.
211 to 264 VAC
183 to 229 VAC
January 2024
IOM-00068-1.0

Advertisement

Table of Contents
loading

This manual is also suitable for:

Iq8+Iq8mIq8aIq8h

Table of Contents