33. Locate the black cover dots from the parts kit and install over the left and right side bracket mounting
holes.
34. Proceed to paragraph 4.3.
Figure 4-3. Removing the Sidecar Rear Shipping Bracket – Eaton 93PM UPS
4.3
Integrated Battery Cabinet Installation
If installing Integrated Battery Cabinets (IBCs), refer to the Eaton 93PM Integrated Battery Cabinet Installation
Manual-Large and Large High Rate, the Eaton 93PM Universal Integrated Battery Cabinet Installation
Manual-Large and Large High Rate, or the Eaton 93PM Integrated Battery Cabinet Installation Manual-Small,
listed in paragraph 1.8, for installation instructions.
After the IBC is installed, proceed to paragraph 4.4 if a Sidecar Integrated Accessory Cabinet-Bypass (SIAC-B)
is attached to the UPS.
4.4
Sidecar Integrated Accessory Cabinet-Bypass Wiring Installation
If an SIAC-B is attached to the UPS, refer to the Eaton 93PM Sidecar Integrated Accessory Cabinet-Bypass
Installation and Operation (50 kW and 100 kW SIAC-B) Manual, listed in paragraph 1.8, for wiring installation
instructions.
After the SIAC-B is wired, proceed to paragraph 4.5 to complete the wiring of the UPS.
Eaton 93PM Emergency Lighting UPS (20–40 kW, 480V Four Wire – UL 924) Installation and Operation Manual P-164000569—Rev 2
NOTE
Black cover dots are provided, if side mounting bracket holes need to be covered for
aesthetic reasons.
Rear Shipping Bracket
UPS System Installation