4 Mounting
16

4.4 Mounting steps with screwed connection

Fig. 7: Screw connection
1
Suspension cable
2
Seal screw
3
Cone bushing
4
Seal cone
5
Screw connection
6
Seal
Mount VEGABAR 66 with screwed connection as follows:
Weld the welded socket into the vessel top
1
Lower VEGABAR 66 to the requested height by means on the
2
welded socket G1½ A or 1½ NPT on the vessel side
Insert the suspension cable from below into the open screwed
3
connection
Slide the seal cone and the cone sleeve over the suspension
4
cable, fasten manually with the seal screw
Screw the screwed connection into the socket, fasten with SW 30
5
and then fasten seal screw with SW 19
How to correct the height:
Loosen seal screw with SW 19
1
Slide seal cone and cone sleeve to the requested position on the
2
cable
Fasten the seal screw
3
Removal is carried out in reverse order.