Switch Sw3/Sw4 Configuration - GE Multilin D400 Instruction Manual

Substation gateway
Hide thumbs Also See for Multilin D400:
Table of Contents

Advertisement

CHAPTER 3: SETTING UP COMMUNICATION CARDS

Switch SW3/SW4 configuration

Switches SW3 (for Channel 2 on TB1-6 through TB1-10) and SW4 (for Channel 1 on TB1-1
through TB1-5) contain ten DIP-switches that control RS-422 pull-up and pull-down
resistors for the differential data lines and provide line termination between the differential
data pairs. Each DIP-switch can be set to ON or OFF to select the appropriate function for
the switch. That is, if all pins are set to ON, switch is ON. If all pins are set to OFF, switch is
OFF.
If RS-422 termination/pull-up is selected, the TX+ and RX+ signals have a 680 ohm pull-up
resistor, the TX- and RX- signals have a 680 ohm pull-down resistor, and the RX and TX
signals have a 120 ohm termination.
Figure 17: RS-485 Mode - 12 KOhm (Single Unit Load))
ON
1
2
3
4
5
6
7
8
9
0
Figure 18: RS-422 120 Ohm Line Termination on TX and RX
ON
1
2
3
4
5
6
7
8
9
0
Figure 19: RS-422 120 Ohm Line Termination with 680 Ohm Pull-Up and Pull-Down
Resistors
ON
1
2
3
4
5
6
7
8
9
0
42
GE INFORMATION
D400 SUBSTATION GATEWAY INSTRUCTION MANUAL

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents