Figure 4-4. Input Power Terminal Locations - 480V/208V - Eaton 93PM Installation And Operation Manual

50 kw (480v/208v) iac-d 50 kw (208v/208v) iac-d 100 kw (480v/208v) iac-d 100 kw (208v/208v) iac-d 150 kw (480v/208v) iac-d 200 kw (480v/208v) iac-d
Table of Contents

Advertisement

Installation
13. Connect phase A, B, and C and Ground power wiring to the corresponding input terminals on the IAC-D.
For a detailed view of the IAC-D input terminals, see Figure 4-5.
14. Connect phase A, B, and C and Ground power wiring to the corresponding output terminals on the UPS.
15. Proceed to paragraph 4.3.3 for 50 kW and 100kW output wiring or 4.3.4 for 150 kW and 200 kW output
wiring.
NOTE The IAC-D is shown with top and bottom panelboards. However, the input and ground terminal locations are the same for all configurations.
Figure 4-4. Input Power Terminal Locations – 480V/208V
4-8
Eaton 93PM Integrated Accessory Cabinet-Distribution (50–200 kW) Installation and Operation Manual P-164000229—Rev 6
480 VAC Input to IAC-D from UPS
(A, B, C)
(See Figure 4-5 for detail.)
UPS Output Breaker
Ground Terminals
www.eaton.com/powerquality