2 Installation and Setup
This section explains how to install, connect, and optimize the projector display.
2.1

Site Requirements

To safely install and operate the D4K35 projector, the installation location must meet these minimum
requirements:
• Physical Operating Environment
• Maximum Ambient Temperature (operating) 35°C
• Minimum Ambient Temperature (operating) 10°C
• External Exhaust Ducting
• The installation site must provide a minimum of 450 CFM (ft
adequate cooling of the Xenon arc lamp at less than or equal to 25°C ambient and less than 3,000 feet ele-
vation. Above 25°C or 3,000 feet, 600 CFM is required. For detailed instructions for measuring CFM, see
Section 2.9 Connect External Exhaust
• Power Connection
• A 30-32A double pole, UL listed wall circuit breaker is required. It must be part of the building installation
and easily accessible.
• Single-phase 30A connection of AC supply to the terminal block.
• Protection from overcurrents, short circuits, and earth faults must be part of the building installation. The dis-
connect device (double pole switch or circuit breaker with minimum 3mm contact gap) must be readily
accessible within the projection room.
NOTE: The requirements listed above are applicable for permanently wired installation or power cord
connection.
2.2

Tools Required for Installation

You need these tools to install the D4K35 projector:
• 12" screwdrivers: Phillips #2 (magnetic) and flat
• 19mm and 7/8" wrenches
• Assorted Allen keys (metric)
• Heat extractor
• Christie approved protective safety clothing if you are working with the lamp
• Lamp
• Lens cleaning tissue and solution
D4K35 Setup Guide
020-100855-02 Rev. 1 (09-2014)
3
Ducting.
/min) external exhaust airflow to ensure