To The Installer - Effecta Komplett III Owner's Manual

A complete pellet boiler
Hide thumbs Also See for Komplett III:
Table of Contents

Advertisement

To the installer

It is time to install the Effecta Komplett III pellet boiler. Please follow the examples we provide
for a safe installation. After installation, be sure to instruct the customer on how the heating
system and the boiler work, in order to avoid unnecessary complications in the future. Please
fill out "Documentation of Settings"(pg35).
Set up
The boiler is positioned so that the
surface temperature of flammable
building material does not exceed
80°C. The boiler must be placed on a
non combustible floor, for example
concrete or tiles. The boiler should
be positioned at least 15 cm (1)
from the wall. The distance from
the flue tube on the boiler to
a flammable wall with ignition
protective covering must be
at least 30 cm (4). In order to
clean the boiler, a minimum
clear space of 1 metre (2)
is required in front of the
boiler and on the side at the
convection section and at
any inspection panel in the
chimney. A passage with a
minimum width of 0.5 (3)
m is required along one of
the long sides of the boiler. Check the regulations of your country in order to place the pellet
hopper on a approved distance from the boiler.
The boiler room
The boiler must be installed in a boiler room or boiler house. The ceilings and walls must
be fitted with ignition protective covering and the floor must be made of non-combustible
material. Minimum ceiling height at the boiler is 2 metres. The boiler room or boiler house
must be equipped with a fresh air intake with the minimum dimensions 150 x 150 (5.) mm or
with a sufficiently large free sectional area to avoid low pressure in the boiler room. It must be
impossible to close the air intake.
Chimney
The draught in the chimney should be about 15 pa at low temperatures. It is important that
the chimney is tested and approved by a HETAS approved installer before a new boiler is
installed. If the chimney has a strong draught, a draught controller (see page 32) may need
to be installed for good boiler operation. If you have a tall chimney and an outgoing flue gas
temperature below 170°C, there is a risk of condensation in the chimney, which can damage
the chimney in the long term. A suitable temperature is 70-80°C one metre down into the
chimney. Ask your local chimney sweep for help to measure the temperature. If the chimney
is tall and has a large area, a draught that is too strong may mean high levels of flue gas and
overignition in the ash compartment. If this is the case, a draft stabiliser must be installed.