Test Operation

1. Test Operation

1.1

Procedure and Outline

Follow the following procedure to conduct the initial test operation after installation.
1.1.1 Check Work Prior to Turn Power Supply On
Check the below items.
Power wiring
Control transmission wiring
between units
Earth wire
Check on refrigerant piping
Check air tight test and vacuum
drying
Check on amount of refrigerant
charge
Check on water piping
72