INSTALLATION SEQUENCE

The typical sequence of installation is outlined below; however, each installation is unique and may result in
variations to the steps described.
See the pages referenced in the following steps for detailed instructions.
Framing
1. Construct the Fireplace Framing (Page 16).
2. Prepare the Fireplace Top Spacers (Page 18).
3. Route the Gas Supply Line to the Fireplace (Page 18).
4. Determining Vent Setup in the Combination Venting Unit (Page 19)
5. Installing Metal, Non-Combustible Front Standoff (Page 19)
6. Rough in the Electrical Supply, if Needed (Page 20).
7. Install the [Optional] Blower Kit before Installation in the Framing (Page 20).
Venting
8. Place the Fireplace in the Framing and Secure (Page 21).
9. Select a Horizontal or Vertical Vent System (Page 21).
10. Install the Vent Restrictor (if necessary) (Page 22).
11. Install the Vent System (Page 25).
Electrical Connection
12. Complete the Field Wiring (Page 37).
13. Install the [Optional] Blower Kit after Installation in the Framing (Page 39).
Gas Connection
14. Connect the Gas Line (Page 40).
15. Verify Proper Fireplace Operation (Page 41).
Finishing
16. Optional: Install the Firebox Liners (Page 58).
17. Install the Logs, Volcanic Stone, and Glowing Embers or Glass Media (Page 58).
18. Install the Glass Door (Page 62).
19. Adjust the Air Shutter to Ensure Proper Flame Appearance (Page 42).
20. Install the Hood in Traditional Fireplaces (Page 43).
21. Reinstall the Included Barrier (Page 44).
22. Install the Finishing Materials and Facade in Contemporary Fireplaces (Page 44).
23. Attach the Safety-in-Operation Warning Labels (Page 47).
24. Installing Batteries for Backup and Wall Switch (Page 44).

Construct the Fireplace Framing

1.
1. Frame the fireplace as illustrated in Table 10. For corner framing installations, use Table 11. All framing details
2. If the fireplace is to be elevated above floor level, a solid continuous platform must be constructed below the fireplace.
NOTE: Headers may be in direct contact with the fireplace top standoff spacers when they are bent up vertically,
maintaining the 4" clearance to the fireplace top, but must not be supported by them or notched to fit around them.
All construction above the fireplace must be self-supporting. DO NOT use the fireplace for structural support.
NOTE: For contemporary models, leave a minimum of 6" clearance to any side wall for proper facade installation and
fit.
16
must allow for a minimum clearance to combustible framing members as shown in Table 8.
Installation
900285-00 05/2015

Advertisement

Table of Contents
loading

Table of Contents