INSTALLATION SEQUENCE

The typical sequence of installation is outlined below; however, each installation is unique and may result in
variations to the steps described.
See the pages referenced in the following steps for detailed instructions.
Framing
1. Construct the Fireplace Framing (Page 16).
2. Prepare the Fireplace Top Spacers (Page 18).
3. Route the Gas Supply Line to the Fireplace (Page 18).
4. Rough in the Electrical Supply, if Needed (Page 19).
5. Install the [Optional] Blower Kit before Installation in the Framing (Page 19).
6. Place the Fireplace in the Framing and Secure (Page 19).
Venting
7. Select a Horizontal or Vertical Vent System (Page 20).
8. Install the Vent Restrictor (if necessary) (Page 21).
9. Install the Vent System (Page 24).
Electrical Connection
10. Complete the Field Wiring (Page 36).
11. Install the [Optional] Blower Kit after Installation in the Framing (Page 39).
Gas Connection
12. Connect the Gas Line (Page 39).
13. Verify Proper Fireplace Operation (Page 40).
Finishing
14. Optional: Install the Firebox Liners (Page 41).
15. Traditional Fireplaces: Install the Logs, Volcanic Stone, and Glowing Embers (Page 41).
16. Contemporary Fireplaces: Install the Glass Media (Page 41).
17. Install the Glass Door (Page 41).
18. Adjust the Air Shutter to Ensure Proper Flame Appearance (Page 41).
19. Install the Hood (Page 43).
20. Reinstall the Included Barrier (Page 43).
21. Install the Finishing Materials (Page 43).
22. Attach the Safety-in-Operation Warning Labels (Page 43).

Construct the Fireplace Framing

1.
1. Frame the fi replace as illustrated in Table 11. For corner framing installations, use Table 12. All framing details
2. If the fi replace is to be elevated above fl oor level, a solid continuous platform must be constructed below the fi replace.
NOTE: Headers may be in direct contact with the fi replace top standoff spacers when they are bent up vertically,
maintaining the 4" clearance to the fi replace top, but must not be supported by them or notched to fi t around them.
All construction above the fi replace must be self-supporting. DO NOT use the fi replace for structural support.
16
must allow for a minimum clearance to combustible framing members as shown in Table 8.

Installation