7.13 Pneumatic connection

7.13.1 Fitting the maintenance unit

The pneumatic connection package is available under order num-
ber 0797 003031. It consists of:
System connection hose
(length 5 m, diameter 9 mm)
Hose connectors and hose clamps
Coupling socket and coupling plug
Correct setting
The system pressure for the pneumatic unit is 8 – 10 bar.
ATTENTION
Machine damage possible due to incorrect pressure.
An incorrect pressure can cause damage to the machine.
Make sure that the system pressure is set to 8 – 10 bar before
fitting the pneumatic unit.
Figure 72: Fitting the pneumatic maintenance unit
1
2
(1) - Cross bar
(2) - System connection tube
1. Attach the maintenance unit (3) to the upper cross bar (1) of
the frame using the bracket, screws and clip.
2. Connect the machine tube (4) coming out of the upper section
to the maintenance unit (3) at the top right.
3. Connect the system connection tube (2) to the pneumatic sys-
tem.
4
3
6
4
8
2
10
0
(3) - Maintenance unit
(4) - Machine tube