Removing and Replacing AC and DC Power Subsystem Components

Troubleshooting a 2800 W DC PEM Installation

Step 1
Step 2
Step 3
Cisco XR 12410 Router Installation Guide
5-26
Use the following procedure to troubleshoot the DC PEM if it is not operating
properly after installation.
Make sure the PEM is seated properly:
Eject and reseat the PEM. Make sure:
The captive screw on the ejector lever is tightened securely.
The power switch is set to the on (1) position.
Make sure the router is powered on and that all power cords are connected
properly.
Check the PEM status indicators:
F1LO (Feeder 1 Low) (flashing yellow)—Indicates that input connections to
the PDU (Feeder 1) were removed, or the input voltage is below the
minimum. Make sure that:
Power cords are securely attached to their PDU terminal studs.
Power cords are securely attached at the DC source end.
The source DC circuit breaker is switched on.
If the indicator is still flashing after you perform the above checks, replace
the power supply.
During normal operation, this indicator remains off.
F2LO (Feeder2 Low) (flashing yellow)—Indicates that input connections to
the PDU (Feeder 2) are removed or the input voltage is below the minimum.
Make sure that:
Power cords are securely attached to their PDU terminal studs.
Power cords are securely attached at the DC source end.
The source DC circuit breaker is switched on.
If the indicator is still flashing after you perform the above checks, replace
the power supply.
During normal operation, this indicator remains off.
Chapter 5
Maintaining the Router