6.
Loosely install the Powerware Hot Sync CAN Bridge Card into the open X-Slot
communication bay on the UPS rear panel.
7.
Repeat Steps 4 through 6 to install a CAN Bridge Card in each UPS to be
paralleled.
NOTE The BladeUPS parallel system can automatically assign identities to each UPS in the system based
on the order in which their CAN Bridge Cards are wired in Steps 8 through 11. For more information, see
"Auto-Identification" on page 87.
8.
Install one of the two supplied blue terminating plugs (see Figure 34) into the
CAN IN port on the first UPS (UPS 1 in Figure 36).
Figure 34. Installing the Blue Terminating Plug (First UPS)
EATON BladeUPS
®
(12 kVA) User's Guide
Blue Terminating Plug (CAN IN)
S
164201649 Rev 4www.eaton.com/powerquality
INSTALLATION
45

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Bladeups 12Bladeups 12i

Table of Contents