Insert The Cage Nuts; Insert The Front Cage Nuts In The Rack - HP Surestore 64 - Director Switch Installation Manual

Fw 05.01.00 and sw 07.01.00 director 2/64 installation guide (aa-rsngc-te/958-000289-001, june 2003)
Hide thumbs Also See for Surestore 64 - Director Switch:
Table of Contents

Advertisement

Figure 11: Securing the two mounting brackets
3. Using a torque driver, torque the screws to 22 in/lb.
4. Locate the two rear mounting plates in the shipping carton.
5. Secure the two rear mounting plates to each side of the switch, as shown in
6. Using a torque driver, torque the screws to 22 in/lb.

Insert the Cage Nuts

Read the following sections for instructions on inserting front and rear cage nuts
in the rack.

Insert the Front Cage Nuts in the Rack

Use these steps to insert the six supplied cage nuts in the rack's front rails:
1. Select one of the front rails.
2. Count up 11 square openings from the top screw of the shelf bracket, and
Director 2/64 Installation Guide
Figure
11. For each plate, use the two flathead countersunk Phillips screws
(10-32 x 0.25 in) provided.
insert the first of three cage nuts.
Installing and Configuring the Director 2/64
53