7.1.4 Restore to normal operation after "EPO - Emergency Power Off" with Load not
supplied
WARNING !
Please check and ensure the conditions of the connected load are safe before
proceeding, as this procedure will result in the connection of power to the load
circuit(s).
NOTE !
Before performing this operation, make sure that the UPS is in the following status:
 "Q1 - UPS Output switch" MUST BE CLOSED (Pos. I).
 "Battery Cabinet Breaker" MUST BE OPEN (Pos. O).
Make sure that SEM Operation Mode is disabled before starting this procedure.
View of the Synoptic Diagram after performed the
command "EPO - Emergency Power Off", with LOAD
NOT SUPPLIED.
1. Restore the "EPO -Emergency Power Off" button.
Press "MUTE" key to reset Alarm and Acoustical Alarm.
LED ALARM remains lit.
2. Perform the "Inverter OFF" command.
Perform the "Inverter OFF" command from the
screen: Commands 1 / Inverter / OFF.
Load is transferred to Utility by Automatic Bypass.
Rectifier starts automatically.
LED 1 (Rectifier) blinking, indicates Soft-start.
At the end of Rectifier Soft-start the LED 1 (Rectifier) remains lit.
The Synoptic Diagram must display the status
"LOAD SUPPLIED BY AUTOMATIC BYPASS".
Modifications reserved
GE_UPS_USM_TLE_SUL_40K_M15_1US_V010.docx
Continue →
Page 62/90
User Manual TLE Scalable Series 40 - 150 UL S1

Advertisement

Table of Contents
loading

Table of Contents