Procedures For Single Tle Series 625 - 750 - 1000; Initial Start-Up Of The Tle Series 625 - 750 - 1000 - GE FGC TLE Series Manual

40-150 kva/kw, 480 vac three phase highly efficient and scalable
Table of Contents

Advertisement

7.1

PROCEDURES FOR SINGLE TLE Series 625 - 750 - 1000

7.1.1 Initial start-up of the TLE Series 625 - 750 - 1000

WARNING !
Before proceeding to turn on the UPS system, ensure that the AC and DC external
isolators are OFF, and prevent their inadverted operation.
Ensure that the Output Load distribution can be powered and all the Output
Isolators are open.
This procedure must be performed for the first start-up following the installation, with the UPS
completely switched Off and not powered.
Open the front door and make sure that:
All the connections to the input/output terminals or bus bars of the UPS have been made correctly.
The safety screens are fixed in their position.
The switch Q1 is open (Pos. O) and the "External Battery Protections" must be open (Pos. O).
Q1
Q1
UPS Output switch
LED ALARM
Command Inverter ON
Command
System shutdown
1. Switch-ON the Utility voltage from the input distribution (both Rectifier and Bypass if
separated).
The UPS performs a "Self-test".
A successful termination of the tests will be indicated with Overall test
results "OK".
Commissioning cannot be continued should one or more tests result
to be negative. Please contact in this case your Service Center.
At this stage the Electronic Power Supply and Control Panel are switched
ON and the Buzzer sounds.
Press "MUTE" key to reset Acoustical Alarm.
LED ALARM remains lit.
Modifications reserved
GE_UPS_USM_TLE_SUL_M62_1M0_2US_V010.docx
Critical Power
LEDs on Synoptic Diagram
LED 1
Rectifier
LED 2
Inverter
LED 3
Booster/ Battery charger
LED LOAD PROTECTED
Command Inverter OFF
System shutdown Reset
LED 4
Automatic Bypass
LED 5
LOAD on UPS
Command
User Manual TLE Series 625 - 750 - 1000 UL S2