GE FGC TLE Series Manual page 391

40-150 kva/kw, 480 vac three phase highly efficient and scalable
Table of Contents

Advertisement

TLE Series 625 - 750 - 1000
PE-Ground connection bus bar configuration for the top cable entry or bottom cable entry
The configuration of the TLE Series 625 - 750 - 1000 is with top cable entry as standard.
It is possible to configure the bus bar with bottom cable entry (see Fig. 4.9-5).
TLE Series 625 & 750
TLE Series 1000
Fig. 4.9-5 TLE Series 625 - 750 - 1000 – PE-Ground connection configuration bus bar with top or bottom cable entry
PE-Ground connection cables are connected to bus bars using M12 bolts.
The bolts of the connection cables must be tightened with a torque wrench at 530 Lb-in / 60 Nm.
TLE Series 625 - 750 - 1000
Battery connection bus bars configuration for the top cable entry or bottom cable entry
The configuration of the TLE Series 625 - 750 - 1000 is with top cable entry as standard.
It is possible to configure the bus bars with bottom cable entry (see Fig. 4.9-6).
Power Section cabinet
TLE Series 625 & 750
Power Section cabinet
TLE Series 1000
Fig. 4.9-6 TLE Series 625 - 750 - 1000 – Battery connection configuration bus bars with top or bottom cable entry
Modifications reserved
GE_UPS_ISG_TLE_SUL_M62_1M0_2US_V010.docx
Critical Power
Q1
Q1
+
_
Position of the bus bars for
cables input from the top of the UPS
cables input from the bottom of the UPS
Battery connection cables
are connected to bus bars
using M10 bolts.
+
_
The bolts of the connection
Position of the bus bars for
cables must be tightened
with a torque wrench at 355
Lb-in / 40 Nm.
Installation Guide TLE Series 625 - 750 - 1000 UL S2
Position of the
PE-Ground bus bar
for cables input from
the top of the UPS
Position of the
PE-Ground bus bar
for cables input from
the bottom of the UPS
Page 43/69

Advertisement

Table of Contents
loading

Table of Contents