Table 7. Tools For Marking - Samsung MT3204 Series Installation Manual

Mmu
Table of Contents

Advertisement

Table 7.
Tools for Marking
Category
Working Tools
To mount the system on a wall, perform the leveling test by referring to the
System Leveling to check the positions are marked to be horizontal or vertical
before drilling. If the result shows they are not horizontal or vertical, modify the
marking positions.
When the position where the system will be placed is determined, place the system
on that position and then mark the positions where anchor bolts will be fixed. This
will reduce marking error range.
1
MT3204 Series Installation Manual v1.0
Copyright © 2018, All Rights Reserved.
Check the distance between the location for fixing the MMU and the anchor
bolt hole.
Chapter 2 Installing System
Description
 Tape Measure
 Permanent Maker
 Level
Confidential