(Figure 5-41: 300kVA UPS_ Parallel Cable Routing-2)
400/ 500/ 600kVA UPS_ Parallel Cable Routing Method (Top & Bottom Entry)
(Step A)
For top entry, use the snap bushing, wire mounts and M4 screws in the accessory package
to install the snap bushing and fasten the wire mounts on the frame.
For bottom entry, use the wire mounts and M4 screws in the accessory package to install
the wire mounts on the frame.
(Figure 5-42: 400/ 500/ 600kVA UPS_ Parallel Cable Routing-1)