400/ 500/ 600kVA UPS_ Signal Cable Routing Method (Top & Bottom Entry)
Step 1
For top entry, use the snap bushing, wire mounts and M4 screws in the accessory package
to install the snap bushing and the wire mounts on the frame. See Figure 4-7
For bottom entry, use the wire mounts and M4 screws in the accessory package to install
the wire mounts on the frame. See Figure 4-7
Step 2
For top/ bottom entry, refer to instructions ❶ ~ ❻ below to properly route and secure the
signal cable with cable ties (user-supplied).
NOTE:
The number of the wire mounts and cable ties shown in the figures are for
reference only. The actual number depends on your on-site application.
Ultron DPS Series
(Figure 4-21: 300kVA UPS_ Signal Cable Routing)