5 Getting Started
5.7 Commissioning
Switch the AC voltages and AC currents to be measured at the measurement object on the measuring
lines.
Carry out the measurements as described in chapter 7.
NOTE
The operation requires JavaScript. If JavaScript is not yet enabled, activate it as described in chapter 7.2.2.
5.7.2

Changes During Operation

The device is designed for permanent operation.
If you want to change the measurement setup, e.g. by connecting terminals so far unused, proceed analogous-
ly to the Initial Commissioning.
NOTE
If you change the measurement setup, you must de-energize the supply voltage lines and all measuring lines
before opening the control cabinet. Please note the warnings in chapter 5.7.1.