Commissioning
6.3 Commissioning on PROFINET IO
6.3.4

Commissioning and startup of ET 200S on the PROFINET IO

Software Requirements
Table 6- 3
Software requirements for commissioning on PROFINET IO
Configuration software
used
STEP 7
Configuration software for
a different IO controller
Requirements for commissioning
The following additional requirements must be satisfied for commissioning the ET 200S on
PROFINET IO:
● IO device installed
● IO device wired up
● IO device has been assigned a device name
● Supply voltage for the DP master is switched on (see manual for the IO controller)
● IO controller is switched to RUN mode (see manual for the IO controller)
Commissioning the ET 200S
To commission the IO device, proceed as follows:
1. Switch on the power supply for the IO device.
2. If necessary, switch on the supply voltage for the load.
120
Version
Version 5.3 and higher and ServicePack 1 for
IM151-3 PN (6ES7151-3AA00-0AB0)
Version 5.3 and higher and ServicePack 3 for
IM151-3 PN (6ES7151-3AA10-0AB0 and higher)
and IM151-3 PN HIGH FEATURE (6ES7151-
3BA20-0AB0 and higher)
Explanations
You use HW Config and the supplied
GSD file.
You need the GSD file from ET 200S.
Operating Instructions, 08/2008, A5E00515771-06
ET 200S

Advertisement

Table of Contents
loading

Table of Contents