4.6 Earthing

Note: Earthing is known as Grounding in some countries.
All Touchpoint Pro equipment must be earthed using the earth terminals provided.
Earth loops must be avoided.
Touchpoint Pro must be connected to protective earth. Connect protective earth (usually mains earth) to the
earth stud marked with the primary earth symbol
Location of primary earth connection point:
Standard enclosure – lower left corner
Rack mount unit – reverse side, lower left corner
The screen of the Ring Network cable and the screens of field device cables should be connected to earth
at the controller, preferably to a clean instrument earth.
The Wall mount enclosures contain a pre-fitted screen bar for earthing the field cables.A suitable
termination is provided for the ring cables and earth terminals for all others.
It is recommended that an earth screen bar be installed in the Touchpoint Pro enclosure / rack to connect
the field and network cable screens.
If armoured or steel wire braided cable is used for field devices, and earthed in the field, it is recommended
that care is exercised to avoid earth (ground) loops by preventing cable armour from coming into contact
with the TPPR enclosure or cable screening.
The diagrams below show some examples of good earthing and screening practice:
P
Incoming
Client
Figure 4.2 Screened cable, plastic junction box and plastic sensor
Earth
4. Electrical Installation
WARNING
Three Core Cable with Screen Earthed at Contoller
. Do not remove any factory fitted earth connections.