I/O Module Installation and Wiring - I/O Module Installation Procedures
Step
Connect wire-tie into the
9
top and/or bottom of the
Rack.
Form a bend in each wire
to provide strain relief, and
secure the wire bundle
with the tie.
Install I/O modules in
10
racks. Be sure to follow
placement guidelines
under Heat Rise De-rating
page 43.
80
Procedure
HC900 Process Controller Installation and User Guide