Replacing The Front Panel Cable; Required Tools; Preliminary Steps - Fujitsu PRIMERGY CX400 S1 Upgrade And Maintenance Manual

Server enclosure
Table of Contents

Advertisement

11.2

Replacing the front panel cable

Field Replaceable Units (FRU)
Average hardware task duration: 80 minutes

11.2.1 Required tools

Preliminary and concluding steps: tool-less
Main steps:
– Phillips PH2 / (+) No. 2 screw driver

11.2.2 Preliminary steps

Perform the following procedures:
"Shutting down the server node" on page 41
Ê
"Removing the server enclosure out of the rack" on page 43
Ê
V
CAUTION!
For ALL service tasks, remove the CX400 S1 server enclosure out of
the rack and put it on a separate desk!
It is not allowed to draw the CX400 S1server enclosure partially out
of the rack.
"Removing the server node from the server enclosure" on page 48
Ê
Ê Remove all HDD/SSD modules as described in section
HDD/SSD modules" on page 106
Ê Remove all HDD modules as described in section
modules" on page 115
"Opening the server enclosure" on page 51
Ê
"Removing the power supply module" on page 84
Ê
Ê Remove both fan modules as described in section
module" on page
CX400 S1
(if applicable)
(if applicable)
137.
Upgrade and Maintenance Manual
Front panel
"Removing 2.5-inch
"Removing 3.5-inch HDD
"Removing the fan
185