QDR InfiniBand Switch Platform User Manual
14.
Tighten the bolts to 9.2 Nm or 81.5 pound inches.
15.
Ground the switch
16.
Plug in the power cables.
17.
Check the Status LEDs and confirm that all of the LEDs show status lights consistent with
normal operation.
18.
You can start connecting all of the cables to the switch.

Figure 47: Power Side View

Figure 48: Connect Bracket to Rack Vertical support

Warning: Any yellow status LEDs is cause for concern and must be
dealt with immediately.
It can take up to 3 minutes to boot up, during which time the status LED
may indicate red.
...
...
...
.