7.
Using two of the pan head screws and two of the washers, for each rail, install the rails to the
end of the rack. Place the rail behind the holes in the rack and screw the screws through the
holes into the rails.
8.
Place the two bolts for the caged nuts within reach.
9.
Slide the switch into the rails.
10. Put the switch into place and screw the bolts into the nuts from step 5.
11. You can start connecting all of the cables to the switch.

2.2.3 Power Connections and Initial Power On

The switch platform ships with one or two Power Supply Units. For switches with only one unit installed, a
second PSU may be installed at a later time. Each supply has a separate AC receptacle. The input voltage is
auto-adjusting for 90-264 VAC, 47-63Hz power connections. The power cords should be standard 3-wire
AC power cords including a safety ground and rated for 15A or higher.
Figure 7: Sc rewing in the Rails
Figure 8: Screw in the Mounting Plates
Caution: The switch platform will automatically power on when AC power is applied.
There is no power switch. Check all boards, power supplies, and fan tray modules for
proper insertion before plugging in a power cable.
Caution: After inserting a power cable and confirming the green system status LED
light is on; make sure that the Fan Status indicator shows green.
If the fan status indicator is not green then unplug the power connection and check that
the fan module is inserted properly and that the mating connector of the fan unit is free
of any dirt and/or obstacles.
Mellanox Technologies
Right hand
mounting plate
9
Rev 1.5

Advertisement

Table of Contents
loading

This manual is also suitable for:

Mts3600r-1uncMts3600q-2uncMts3600r-2unc

Table of Contents