Chapter 2 Mechanical Installation
25

2.7 Installation Inspection

After the mechanical installation is completed, you should check that:
1. A certain space is left around the unit for maintenance. For details, see Maintenance space requirement in
2.3.1 Installation Requirement;
2. The equipment is installed vertically and the installation fasteners have been fixed;
3. The pipes connecting the indoor unit and outdoor unit have been connected;
4. The condensate pump (if needed) has been installed;
5. The drain pipe has been connected;
6. The water supply pipe for infrared humidifier has been connected;
7. All pipe joints have been fixed;
8. The transport fasteners have been removed;
9. The water level regulator of the infrared humidifier has been unscrewed to the required height;
10. The debris (such as transportation materials, structure materials and tools) inside or around the
equipment has been cleaned.
After confirming the preceding points, you can then start the electrical installation.
Liebert.PEX Chilled Water Series Air Conditioner User Manual

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Liebert pex p3110vc2ms1rz00

Table of Contents