Scsi Hard Drive Installation - HP ProLiant DL145 User Manual

Hide thumbs Also See for ProLiant DL145:
Table of Contents

Advertisement

Hardware Options Installation
7. Install the PCI-X riser cage.
Figure 4-27: Installing the PCI-X riser cage
8. Connect any required cables to the expansion board.
9. Reinstall the access panel.
10. Restore the server to its operating position in the rack.
11. Power up the server.

SCSI Hard Drive Installation

To prepare the server for SCSI hard drive installation, perform the following steps:
1. Power down the server. Refer to "Powering Down the Server" in Chapter 2, "Server
Operations."
2. Extend the server from the rack. Refer to "Extending the Server from the Rack" in
Chapter 2, "Server Operations."
3. Remove the access panel. Refer to "Removing the Access Panel and the Chassis
Stiffener" in Chapter 2, "Server Operations."
4. Remove the chassis stiffener. Refer to "Removing the Access Panel and the Chassis
Stiffener" in Chapter 2, "Server Operations."
5. Remove the EIDE hard drives. Refer to "Removing the EIDE Hard Drives"" section
earlier in this chapter.
4-18
HP ProLiant DL145 Server User Guide

Advertisement

Table of Contents
loading

Table of Contents