3) With the key switch in the STOP position, the AC IN and the BYP lamp will be "on"
and the LCD screen should display the following message:
4) Turn the Key Switch to "RUN" and the UPS automatically performs a controlled
system battery test. (Note: The Automatic Battery Test is performed only when the
software is enabled for this function. The standard default is set to disable.)
(Allow 24-72 hours for the batteries to fully charge).
When automatic battery test fails and the "LOW BATTERY" message is displayed use the
following procedure:
1) Turn the key switch to STOP.
2) Allow 24-72 hours for the batteries to charge and then move the Circuit Breaker to
"off."
3) Repeat Initial Battery Charge procedure. (A failure indicates battery replacement
may be necessary).
6.15

Start-up Procedure

The UPS batteries must be charged before the UPS is used for the first time or if the unit
has not been used (AC power source removed) for more than 10 days. If the batteries are
charged then use the following start-up procedure:
1) Verify that all power switches are off, and that the "STOP/RUN" Switch on the UPS is
in the "STOP" position.
2) Switch on the power at the Customer Provided UPS input distribution panel.
3) Move the UPS Circuit Breakers to "on." The AC IN lamp will be "on." The LCD screen
should display the following message:
With the key switch in the "STOP" position, both the AC IN and the BYP lamp will be "on"
and the LCD screen should display the following message:
4200FA Installation and Operation Manual
- BYPASS OPERATION -
OUTPUT VOLTAGE=208 V
>CURRENT 100/100/100%
(DATE) DAY (TIME)
- UPS START UP -
> PLEASE WAIT
- BYPASS OPERATION –
OUTPUT VOLTAGE=208 V
>CURRENT 100/80/90%