STEP 2: Slide Side Plates in along C-Channel
base.
2.1
Facing the front of the UPS, slide a side kick plate with the smooth side
facing out down along the left base C-channel skid until it is protruding
about one inch in front of the UPS. See Figure B2.
2.2
Repeat for the right C-channel skid.
STEP 3: Align the F/B Plate with the UPS front.
Place a F/B kick plate on the floor as in Step 1. Angle the right edge out away
from the UPS until the pair of front slots at the ends of the F/B kick plate are
visible. See Figure B3.
STEP 4: Insert Side Plate tabs into F/B
Plate slots.
Insert the side plate tabs into the F/B kick plate slots on the
floor in front of the UPS, and then slide the right edge out until
the pair of front slots at each end of the plate are visible. See
Figure B3.
4.1
Carefully slide the F/B kick plate forward until the Side
plate tabs are inserted in the F/B kick plate slots. (NOTE
- This is a snug fit.)
4.2
Slide the right side of the F/B kick plate forward to en-
gage the tabs of the right Side kick plate.
4.3
Slide the F/B kick plate forward until the left and right
Side kick plate magnetic latches make contact with the
F/B kick plate.
4.4
Slide the F/B kick plate back until it make contact with
both the C-channel base skids.
STEP 5: Attach the rear F/B Plate to the back of the UPS
Repeat Step B4 for the F/B kick plate at the rear of the UPS.
74
Figure B2
Figure B3
4300 Series Installation and Operation Manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

4310f3f3004310f3f500

Table of Contents