Mounting
24
9
Performing the zero adjustment
1. Let the system run until normal operating conditions are present.
2. Stop the flow (v = 0 m/s (0 ft/s)).
3. Check the shutoff valves for leaks.
4. Perform adjustment using the Zero point adjustment control function.
6.2
Mounting the measuring instrument
6.2.1
Required tools
For process connections, use the appropriate installation tool
6.2.2
Preparing the measuring instrument
1. Remove all remaining transport packaging.
2. Remove any protective covers or protective caps present from the sensor.
3. Remove the transport label on the transmitter housing.
6.2.3
Mounting the measuring device
WARNING
L
Danger due to improper process sealing!
‣
Ensure that the inside diameters of the gaskets are greater than or equal to that of the
process connections and piping.
‣
Ensure that the seals are clean and undamaged.
‣
Secure the seals correctly.
‣
Ensure that the direction of the arrow on the nameplate of the sensor matches the flow
direction of the medium.