The cable tray and cable trough on the top of the cabinet must be kept at a
certain height.
Figure 5-2 Cable tray and cable trough requirements for cabinets connected in
parallel (unit: mm)
(1) Cable tray and cable
trough

5.2 Installation Preparations

5.2.1 Tools

The onsite operation personnel can select tools based on the site requirements.
Issue 09 (2024-01-31)
NO TE
The cabinet can be installed with one side against a wall. It is recommended that the
distance between the cabinet side and the wall be at least 400 mm.
It is recommended that the cable tray and cable trough face the cable outlet
on the top of the cabinet.
If multiple cabinets share one cable trough, the size and bending angle of the
cable trough must meet the requirements on the minimum bending radius of
cables. For details about the minimum bending radius, see the technical
specifications of cables.
The cable tray and cable trough need to be prepared by the customer. The
appearance shown in the figure is for reference only. The actual site survey
data applies.
Copyright © Huawei Digital Power Technologies Co., Ltd.
(2) Two cabinets connected in
parallel
5 Installation and Cable Connection
(3) Three cabinets connected
in parallel
52