SmartLi 3.0
User Manual (Long-Term Backup Power)
Context
Set the circuit breaker based on the actual load. If the load of a single battery
cabinet is greater than 50 kW and less than or equal to 100 kW, set I1 to the MED
position and select a 95 mm
than or equal to 50 kW, set I1 to the MIN position and select a 70 mm
Figure 5-15 Setting the battery circuit breaker
(1) 50 kW < Load of a single battery cabinet ≤
100 kW
Procedure
Step 1 Remove the cable gland nuts and sealing plugs from the top.
Figure 5-16 Top cable glands
(1) Positive cable outlet
(gland: M40)
Step 2 Cut cables and crimp terminals.
Issue 09 (2024-01-31)
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
2
cable. If the load of a single battery cabinet is less
(2) Load of a single battery cabinet ≤ 50 kW
(2) Neutral cable outlet (gland:
M40)
5 Installation and Cable Connection
(3) Negative cable outlet
(gland: M40)
2
cable.
70