Downloading Test Data - Huawei SmartLi 3.0 User Manual

Hide thumbs Also See for SmartLi 3.0:
Table of Contents

Advertisement

SmartLi 3.0
User Manual (Long-Term Backup Power)
Figure 7-2 Starting a capacity test
----End

7.3 Downloading Test Data

Procedure
Step 1 On the UPS WebUI, choose Query > Battery Test Records, choose logs that need
to be queried from the Log drop-down list box, and click Query.
Figure 7-3 Battery Test Records
Step 2 Choose logs that have been queried from the Log drop-down list box, and click
Export.
----End
Issue 09 (2024-01-31)
NO TE
The capacity test automatically stops in any of the following cases:
● The minimum cell voltage reaches 2.65 V.
● The load fluctuation exceeds 10%.
● An alarm is generated.
The test is complete when the minimum cell voltage reaches 2.65 V. A maximum of recent
36 capacity test records can be saved.
Copyright © Huawei Digital Power Technologies Co., Ltd.
7 Maintenance
115