Commissioning

7.1

Insulation resistance test

Only appropriately qualified technical personnel knowledgeable about the subject matter may
install and commission the system. The technical personnel are also familiar with work
protection regulations, safety regulations and the relevant domestic regulations. For accident
prevention, apply the corresponding laws and regulations applicable in the country as well as
safety equipment when mounting and operating the motor.
Unintentional starting of the drive unit
Secure the drive unit to prevent it from being started up unintentionally.
Attach a warning notice to the start switch.
Hazardous voltage and rotating parts
Before starting commissioning, mount the covers required for the correct air guidance.
Never touch active, live or rotating parts and components.
Hazardous voltage at the terminals
The terminals can be at hazardous voltage levels during the measurement and immediately
afterwards. The terminals must not be touched.
With the power cables connected, check that no voltage is applied.
Note
Check the insulation resistance before commissioning and after longer periods of storage or
non-operational periods.
Before you begin measuring the insulation resistance, read the operating manual for the
insulation resistance meter you are going to use. If a main circuit line is already connected for
measuring the insulation resistance, remove it from the terminals.
Motors for mounting onto SIMOGEAR gearboxes
Operating Instructions, 01/2024, A5E53220841A/RS-AA
WARNING
WARNING
WARNING
7
83

Advertisement

Table of Contents
loading

Table of Contents