Installer Manual Fleck 9000 - SXT - Installation
5.7.
Regeneration types
Metered
The controller monitors the volume of water used. Once it calculates that there is not enough capacity
for the next operation day, a regeneration cycle will be initiated immediately or at a pre-set time:
•
immediate control: the controller measures water usage and regenerates the system as soon
as the system capacity is reached;
•
delayed control: the controller measures water usage and if the capacity is not reached until the
number of days override, it regenerates the system, at the specified regeneration time.
5.8.
Electrical connections
42 / 108
W1: Black
W2: Red
W3: Green
W4: Yellow
W5: White
W6: Blue
W7: Orange
W8: Violet
Ref. MKT-IM-020 / B - 08.06.2018