Commissioning

Gas fitting connection
Electrical connection
Checks before commissioning
All electrical installation and
connection work must only be carried
out by a suitably qualified electrician.
N.B.: The applicable
guidelines and directives
must be observed, as well as
the electrical circuit diagram
supplied with the burner.
Before connecting the burner, it is
essential to ensure that the entire
burner has reached the ambient
temperature. Otherwise, there is a
risk that condensation will form on
electronic components resulting in
damage to property and personal
injury!
Checks before commissioning
The following must be checked before
initial commissioning:
• That the burner is assembled in
accordance with the instructions given
here.
• That the burner is pre-set in
accordance with the values in the
adjustment table.
• Setting the combustion components.
• The heat generator must be ready for
operation, and the operating
regulations for the heat generator
must be observed.
Gas fitting connection
The connectors on the burner must be
used for connecting the gas valve.
Cognisance must be taken of the
equipment labelling and the electrical
circuit diagram.
Electrical connection
The electrical connections, i.e. the
installation materials and all the
connectors and earth/ground
connections, must be installed in
compliance with the specifications.
The electrical installation of the burner
must be carried out in accordance with
the circuit diagram drawn up for the
furnace.
• All electrical connections must be
correct.
• The heat generator and heating
system must be filled with water and
the circulating pumps must be in
operation.
• The temperature regulator, pressure
regulator, low water detectors and any
other safety or limiting devices that
might be fitted must be connected and
operational.
• The exhaust gas duct must be
unobstructed and the secondary air
system, if available, must be
operational.
03/2016 - Art. Nr. 4200 1044 8002A
The electrical connection of the burner
may only be performed by authorised
specialists.
Please note:
When installing the connection cable,
the cable loops selected must be large
enough to allow the boiler door to swivel
open. When electrical connection work
is complete, the wiring for the burner
electrics must be checked. This includes
checking the direction of rotation of the
fan or the fuel-oil pump motor.
• An adequate supply of fresh air must
be guaranteed.
• A heat dissipation system must be
available.
• Sufficient gas pressure must be
available.
• The fuel supply lines must be
assembled correctly, checked for
leaks and bled.
• A standard-compliant measuring point
must be available for measuring the
exhaust gas, the exhaust gas duct up
to the measuring point must be free of
leaks to prevent anomalies in the
measurement results.