ABB Relion 670 Series Commissioning Manual page 86

Transformer protection
Hide thumbs Also See for Relion 670 Series:
Table of Contents

Advertisement

Section 9
Establishing connection and verifying the IEEE C37.118/1344 communication
IEC140000143 V1 EN-US
Figure 15:
Open the capture file and observe the captured synchrophasor data. In order to get the
Phasor names on top of each column (See figure 16), the capture process should start
before connecting the PMU Connection Tester to the PMU, i.e. first start the capturing and
then click
80
Stop capturing the IEEE C37.118 synchrophasor data
Connect .
© Copyright 2017 ABB. All rights reserved
1MRK 504 165-UEN E
IEC140000143-1-en.vsd
Transformer protection RET670