ommissioning
Do not place objects of any kind on the inverter during operation!
Do not touch the heat sink while the inverter is operating!
Some parts may be very hot and could cause burns.
b01
b02 b03 b04
b11
Before proceeding with commissioning, make sure you have carried out all the checks and
verifications indicated in the section on preliminary checks.
Config. Wizard
ENTER to START
ENTER
Time hh:mm
Date DD MMM YYYY
ENTER
Input Mode
PARALLEL/INDEP
ENTER
GRID=Xxxxxxxx
Lang=Xxxxxxxx
b05
b06
b07
b08
b13
b12
b24
The procedure for commissioning the inverter consists of the following
steps:
• Close the AC disconnect switch to supply the inverter with the grid
voltage
• Close the DC disconnect switch to supply the inverter with the photo-
voltaic generator voltage.
If the inverter is equipped with a DC disconnect switch (-S models), turn
the DC disconnect switch
• When the inverter is connected to the power supply, the display will
show a guided configuration procedure. Press ENTER to set the fol-
lowing:
- Inverter date and time
- Parallel or independent mode configuration of the input channels
The inverter is shipped from the factory with the input channels set to
INDEPENDENT. Should you decide to use the channels in PARALLEL
mode, you should fit the special jumpers supplied and select the correct
input configuration mode
- Selection of grid standard and corresponding display language.
- 72 -
b09
b10
DC
AC
b14
b15
b16
to the ON position.
14
7 - Operation
01
b19
b22
b21
b20
b17
b18

Advertisement

Table of Contents
loading

This manual is also suitable for:

Trio-7.5-tl-outd-sTrio-8.5-tl-outd-s

Table of Contents