1MRK 511 409-UUS Rev. K
4.4.2

IED start-up sequence

When the IED is energized, the green LED starts flashing instantly. After approximately 55 seconds the
window lights up and the window displays 'IED Startup'. The main menu is displayed and the upper row
should indicate 'Available' after about 90 seconds. A steady green light indicates a successful startup.
1
0
IEC04000310 V2 EN-US
Figure 2:
1 IED energized. Green LED instantly starts flashing
2 LCD lights up and "IED startup" is displayed
3 The main menu is displayed. A steady green light indicates a successful startup.
If the upper row in the window indicates 'Fail' instead of 'Available' and the green LED flashes, an
internal failure in the IED has been detected.
4.5

Setting up communication between PCM600 and the IED

The communication between the IED and PCM600 is independent of the communication protocol used
within the substation or to the NCC.
4.5.1

When IED has blank front panel

IED with blank front panel will not have front port. Instead in the IED's AP1 will be turned on which will
have the default IP address 192.168.1.10 and subnet mask 255.255.255.0. If the user wants to change
the default IP address, use RIA600 or PCM600.
4.5.2

When IED has front port with RJ-45

The communication media is always Ethernet and the used transport layer is TCP/IP.
Each IED has an RJ-45 Ethernet interface connector on the front. The front Ethernet connector is
recommended to be used for communication with PCM600.
When an Ethernet-based station protocol is used, PCM600 communication can use the same Ethernet
port and IP address.
To connect PCM600 to the IED, two basic variants must be considered.
Phasor measurement unit RES670
Commissioning manual
2
t1
xx04000310-1-en.vsd
Typical IED start-up sequence
DHCP is not available on this port.
© 2017 - 2022 Hitachi Energy. All rights reserved
3
t (s)
t2
Section 4
Starting up
M11727-3 v13
SEMOD58570-5 v16
GUID-8BBF8B90-8E20-428D-82EE-18F36D5C8054 v1
GUID-9EE3E4F1-1BD8-49D3-9221-A43D7F8A99AD v1
33

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion 670 series

Table of Contents