Optical Budget Calculation For Pmu - Pdc Communication - Hitachi Relion RES670 Commissioning Manual

Phasor measurement unit
Hide thumbs Also See for Relion RES670:
Table of Contents

Advertisement

1MRK 511 409-UUS Rev. K
9.6

Optical budget calculation for PMU - PDC communication

Most of the times, the PMU IEDs are located in the substations. A local PDC might be located in the
substation. For communications within the substation or between the IED and the WAN/LAN access
point, it is important to know what is the optical budget available. The graph in Figure
dynamic range available for a PMU – PDC configuration using typical OEMs.
14
12
10
8
6
4
2
0
0
IEC11000409 V1 EN-US
Figure 18:
As shown in the graph, if one uses a 62.5/125 µm fiber, the value under the 62.5/125 µm curve
represents the remaining optical budget at any link length, which is available for overcoming non-fiber
cable related losses.
Losses in the connectors and splices are typically 0.3dB/connection. The user must reserve 3dB spare
for the uncertainty of the measurements.
Phasor measurement unit RES670
Commissioning manual
62.5/125 µm
50/125 µm
0.5
1.0
1.5
2.0
2.5
FIBER OPTIC CABLE LENGTH - km
IEC11000409_1_en.vsd
Optical power budget for fiber optic cable lengths
© 2017 - 2022 Hitachi Energy. All rights reserved
Establishing connection and verifying the IEEE C37.118/1344 communication
3.0
3.5
4.0
Section 9
GUID-F5DEACB1-4B83-4C68-B59A-694CAC78AF3D v3
18
shows the
65

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion 670 series

Table of Contents