INSTALLATION

COOLER METHOD OF INSTALLATION

There are two possible methods of installation for the cooler:
1.
Installation via crane (preferred) – cooler is lifted from its
pallet on the ground and slung onto the supply duct.
2.
Piece by piece assembly – cooler is disassembled on the
ground and reassembled on the supply duct.
The ideal method of installation will be specific to each
assignment. To determine which method is best suited to your
installation, be sure to consider regulations, location, access
points, potential obstacles and safety.
Discuss the possible options with the customer.

PREPARING TO LIFT THE COOLER

IT IS THE RESPONSIBILITY OF THE RIGGER TO
DETERMINE THE APPROPRIATE METHOD AND
EQUIPMENT FOR LIFTING THE COOLER.
The cooler may be lifted by crane via slinging only. Slinging
points have been provided. Slings must comply with National
Standards.
DO NOT LIFT USING ANY CABINET FEATURES,
ALTERNATE SLING LOCATIONS OR BY RETRO-FITTING
LIFTING LUGS.
The cabinet may be damaged and/or lift safety may be
compromised.
DO NOT ATTEMPT TO LIFT THE COOLER WITHOUT THE
FOAM SUPPORTING BLOCKS.
If they are missing or damaged, contact the dealer and/or resort
to the 'piece-by-piece' method of installation.
DO NOT ATTEMPT TO LIFT THE COOLER ON THE PALLET.
It is not possible to fit the cooler to the supply duct if the pallet is
used to sling the cooler.
Before the cooler is lifted:
Inspect the cooler to make sure it is in good condition.
Ensure all exterior panels and clips are firmly in place.
Contact the dealer if any exterior components appear to be
structurally damaged.
Ensure the power cable has been passed through the rear
access hole and is taped to an exterior cooler panel.
Ensure the foam support blocks and cooler have not
moved from their dedicated positions in transit.
Inspect the structural integrity of the foam support blocks
to ensure they are in good condition. The foam supports
to the tank for lifting and provides retention channels for
slings.
Make sure the foam support blocks are firmly inserted
upwards into the female openings in the underbody of the
tank.

LIFTING THE COOLER

Place the slings underneath the cooler and through the
dedicated recess channel in the foam supporting blocks.
Rocking, lifting and/or blocking up the front of the cooler will be
required to pass slings beneath cooler while it sits on the pallet.
Important! Two people are required to guide the cooler onto
the supply duct.
Lift and suspend the cooler approximately 100mm (4") above
the transition.
Check the orientation of the cooler to make sure it is in the
correct position with the branding on the front of the cooler
positioned at the front of the supply duct.
ILL3026-A