Step 3 Lead the other end of the FE/GE cable out of the cabinet through the cable hole at the bottom
along the right of the cabinet.
Step 4 Route the cable along the right of the cabinet by referring to
then use cable ties to bind the cable.
Step 5 Label the installed cables by referring to Attaching an L-Shaped Label.
----End

12.4.3 Installing the FE/GE Optical Cable

This section describes the procedure and precautions to be taken for installing an FE/GE optical
cable.
Context
l
l
The performance of an optical module that is exposed to the air for more than 20 minutes may
be abnormal. Therefore, you must insert an fiber optic cable into an unpacked optical module
within 20 minutes.
Procedure
Step 1 Insert an optical module into the corresponding FE/GE optical port, as shown in
12-29.
Step 2 Insert one end of the FE/GE optical cable into the optical module, as shown in
Figure 12-29 Installing the FE/GE optical cable
Issue 01 (2011-10-25)
The single-mode optical module is labeled "SM" and multi-mode optical module is labeled
"MM".
If the puller of an optical module is blue, the module is a single-mode optical module. If
the puller of an optical module is black or grey, the module is a multi-mode optical module.
NOTE
The procedures for installing FE/GE optical cables in an APM30H and in an TMC11H are the same. The
following description is based on the procedure for installing an FE/GE optical cable in an APM30H.
CAUTION
NOTE
For details about how to connect the FE/GE optical cable, see Transmission Cable Connections.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
12 Installing the Cables
12.1 Cabling
Requirements, and
Figure
Figure
12-29.
114

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Bts3900a wcdmaBts3900a lteBts3900a gsm

Table of Contents