Figure 12-54 Installing the monitoring signal cable in the scenario of 1 RFC+2 TMC11Hs
Step 2 Attach labels to the installed cables. For details, see Attaching an L-Shaped Label.
Step 3 Run each cable that leave the cabinet in a PVC corrugated pipe, and then tie the pipe to the cable
hole in the cabinet.
Step 4 If two RFCs and two TMC11Hs are configured on site, one more monitoring signal cable is
required.
Figure 12-55 Configurations of two RFCs and two TMC11Hs
Issue 01 (2011-10-25)
Figure 12-55
shows the configurations of the cabinets.
Huawei Proprietary and Confidential