UPS5000-E-(30 kVA–180 kVA)
User Manual (Integrated UPS)
Non-Secured Installation
Step 1 Raise the four anchor bolts at the bottom of the UPS cabinet by using a wrench
until all the four castors at the bottom hang in the air and the anchor bolts bear
all of the cabinet weight.
1. Wrench an anchor bolt clockwise to elevate the cabinet, or wrench it
2. To prevent cabinet tilting, adjust the four anchor bolts instead of one anchor
3. Use a measuring tape for measurement when leveling the cabinet to ensure
4. Do not remove anchor bolts. Otherwise, you need to rework them for use.
Step 2 Check the cabinet levelness using a level. If the cabinet is not level, wrench the
anchor bolts.
Figure 3-10 Adjusting the leveling feet
----End
Installing the Cabinet on an ESD Floor
A support is required when the UPS is installed on an ESD floor. The support
height depends on the height between the ground and the ESD floor.
Step 1 Lift the UPS onto the support and align the UPS mounting holes with those on the
floor.
Step 2 Level the UPS by adjusting the anchor bolts and using a level.
Issue 02 (2022-12-30)
NO TICE
counterclockwise to lower the cabinet. The anchor bolts can be wrenched
within a range of 0–8 mm.
bolt.
that the height between the cabinet top and the floor is 2000 mm (tolerance
+3 mm).
Copyright © Huawei Digital Power Technologies Co., Ltd.
3 Installation
58