2.2 Installing the Switch

This section describes how to install your Managed Switch and make connections to the Managed Switch. Please read the
following topics and perform the procedures in the order being presented. To install your Managed Switch on a desktop or shelf,
simply complete the following steps.

2.2.1 Wall Mount/Magnet Installation

2.2.1.1 Wall-mount installation

To install the Managed Switch on the wall, simply follow the following steps:
Step 1:
There are 4 holes with 8mm diameter on the wall;
WGS-804HPT/WGS-4215-8T: the distance between the 2 holes is 133mm
WGS-4215 Series: the distance between the 2 holes is 163mm
WGS-4215-16P2S: the distance between the 2 holes is 230mm
Note: The line through them must be horizontal.
Step 2:
Install a conductor pipe inside the board hole and flush the edge of the conductor pipe with the wall
Step 3:
Screw the bolts into the conductor pipe. The Wall-mount Managed Switch is between bolts and conductor pipe, as
shown below.